Re: Internal Move Waiting for another Move

by
XPANSA, Eva Pinter
- 08/28/2015 03:46:50

Hi Hardianto,

You nay face quite a lot of limitations using standard Odoo for manufacturing . From my humble point of view v7 does not allow to implement real manufacturing processes. I would encourage the company to move to v8 if they have any will to do serious manufacturing with operations and proper work center management.

On 28 Aug 2015 05:07, "Hardianto Darjoto" <hardi@telenais.com> wrote:
Hi Eva,

The reason is just because the company extend their business into manufacturing. They are already OE7 user for trading / distribution.

Thanks for your response.

Hardianto Darjoto
Odoo the new OpenERP
open-source business apps
www.telenais.com
Tel.+62-21-83709595

On Fri, Aug 28, 2015 at 8:38 AM, Eva Pinter @ xpansa <eva.pinter@xpansa.com> wrote:

Hi Ardiante,


Do you have a special reason to set-up manufacturing on OE7? Please check out OdooMRP on GitHub, as this has a huge number of corrections and extensions for production and really allows to manage full manufacturing.

It’s only available on Odoo v8, but is so stable, that I would encourage you to move to Odoo V8.

-- 

Best Regards,
Eva Pinter


Sales and Marketing Director, XPANSA Logistics | ERP, BI, E-commerce, Data Mining and DMS consulting
Xpansa CLOUD | Full Business IT Infrastructure | https://xpansa.com/products/xpansa-odoo-alfresco-bi-saas/
mERP | Odoo Android App | merpapp.com

/// site  : xpansa.com
/// mail  : eva.pinter@xpansa.com
/// phone, IE : +44 (0)7596 40 30 99
/// skype : epinter

On 28 Aug 2015, at 01:34, Hardianto Darjoto <hardi@telenais.com> wrote:

Hi all,

I just find this problem, in OE7

When creating and confirming Manufacturing Order (MO), it created stock move:

Internal Move: Warehouse/Stock/Shelf > Warehouse/Stock

and will be followed by:

Warehouse / Stock > Virtual Production (Raw Material)
Virtual Production > Warehouse / Stock (Finished Goods)

If raw material available before MO confirmed, no problem. The workflows functioned well.

If raw material not available when MO confirmed, the status of first Internal Move will be "Waiting Another Move".

If we procure the RM and then put these RM in the location, it won't change the status. Still "waiting for another move" (>>what move?). And MO process stuck here.

I've just found this now because I used to work with Order Points rule for RM with Make To Stock, so there will be always RM available in Stock. Now I work with different stock policy (Make to Order), in which there will be possibility RM not available in Stock, and we just know no stock when triggerred by MO

but the problem still persist.

Is anybody here has the same experiences and solution?

Thanks

Hardianto Darjoto
Odoo the new OpenERP
open-source business apps
www.telenais.com
Tel.+62-21-83709595

_______________________________________________
Mailing-List: https://www.odoo.com/groups/community-59
Post to: mailto:community@mail.odoo.com
Unsubscribe: https://www.odoo.com/groups?unsubscribe


_______________________________________________
Mailing-List: https://www.odoo.com/groups/community-59
Post to: mailto:community@mail.odoo.com
Unsubscribe: https://www.odoo.com/groups?unsubscribe


_______________________________________________
Mailing-List: https://www.odoo.com/groups/community-59
Post to: mailto:community@mail.odoo.com
Unsubscribe: https://www.odoo.com/groups?unsubscribe