why is Tasks estimated Time different from duration in gantt view ?

By
hassen
on 4/24/13, 4:17 PM 948 views

I have a task with estimated time of let's say 12h. when I look at that task in gantt view the duration displayed is completly different (it may be 9.3333 or something else). can somebody please explain to me the reason for this difference ?

Have the same problem; I believed first this was related to the "working time" parameter in the related project, but this parameter was not even set....

Marc Cassuto
on 9/11/13, 12:29 PM

Hi, do you find the problem? We have the same, but not solution... thank's

Natys, Natys
on 10/30/13, 12:55 PM

Your Answer

Please try to give a substantial answer. If you wanted to comment on the question or answer, just use the commenting tool. Please remember that you can always revise your answers - no need to answer the same question twice. Also, please don't forget to vote - it really helps to select the best questions and answers!

About This Community

This community is for professionals and enthusiasts of our products and services. Read Guidelines

Question tools

0 follower(s)

Stats

Asked: 4/24/13, 4:17 PM
Seen: 948 times
Last updated: 3/16/15, 8:10 AM