In the BOM list view, there are the columns "BOM Type" and "Method". There is no field labelled "method" when editing the BOM. What is this method?


Ray Carnes

--Ray Carnes--
| 9 7 9
Greater Los Angeles, United States
--Ray Carnes--

Senior Odoo Analyst

OpenERP 6.1, 7.0 and Odoo 8.0, 9.0 (Since 2012)

Completed Functional and Technical Training.

Major Skills:

  • Needs Discovery and Requirements Analysis;

  • Function and Technical Specifications;

  • Project Planning;

  • Prototyping and Proof of concepts;

  • Data migration;

  • Configuration & Customization (UI and modules);

  • Integration - data, business logic and service levels;

  • Training and Knowledge transfer;

  • Go Live support;

  • Help desk;

  • Version Migration.

I have over 20 years of experience empowering and enabling users with enterprise information systems that make a real and measurable difference in their ability to proactively manage their businesses and organizations. 

Ray Carnes
On 3/18/13, 11:09 PM

The BOM's Method is a property of the BOM which is set automatically based on the Procurement Method of the BOM's product and the type of BOM. It is not editable directly

Type is either Normal BoM or Sets/Phantom.

If a product is used to make several products, it can be useful to create its own BoM - think of a white sauce used to make different dinners. The sauce would be a sub-product.

If you don't want separate manufacturing orders (one for the sauce, one for the dinner) select Sets/Phantom as the BoM type - when you do this a single list of components will be shown on the manufacturing order.

If a Phantom BoM is used for a standalone product, it will be sold and shipped as a set of components (like a kit), instead of being manufactured.

The BOM Method is either On Stock, On Order or Set/Pack.

If Type is Sets/Phantom and the BOM is for a standalone product, the BOM Method is Set/Pack.

If the Procure Method is Make to Stock, the BOM Method is On Stock.

If the Procure Method is Make to Order, the BOM Method is On Order.

About This Community

This community is for professionals and enthusiasts of our products and services. Read Guidelines

Question tools

1 follower(s)


Asked: 3/18/13, 10:45 PM
Seen: 4866 times
Last updated: 6/2/15, 6:54 PM