Checked the bug, seems like it showing as fixed. This is not the case and it is still broken. Pretty fundemental that I can have my PO's showing expected date as the correct date.. Any work arounds in the mean time?

0
0
Emily United Kingdom
3/20/18, 6:58 AM

Does anyone have a solution for this yet? I'm having a lot of problems with the scheduling of work orders too mainly with them being scheduled for the exact same day and time even though the efficiency factor of the work centre has been set to 1?

0
mauro anelli Italy
11/17/17, 4:08 AM

any solution yet?

0
Eltjo Reijenga Netherlands
11/29/15, 4:03 PM

Is there a solution to this issue yet?

I'm using v8 with JIT

0
Philippe Ecrement France
6/12/13, 7:02 AM

I have the same problem than you. In fact OpenERP uses production time and delivery time of product to schedule your purchase order in the past in order to have it ready for... today. This is really a pain because it does it even if you product need (sale in my case) is scheduled for 6 months later. I also tried to put some stock (10 in stock for a sale order of 11) . FYI I'm not using JIT module.

Well to summarize the MRP is not functionning for planning purchase according to your sale planning. A big miss actually.

1 Comment
E.R. Spada II United States
8/4/15, 2:21 PM

Major bug, still an issue

0
Mohammed Mansour Egypt
9/12/14, 6:24 PM

The quotation order date is determined as follow :

Expected Date in the generated procurment order = Sale Order Date (on the SO) + Customer Lead Time (on the SO line, coming from the product) - Security Days (on the company).

Expected Date = Expected Date in the generated procurment order - Purchase lead time ( in your company definition ---> configuration tab ).

Quotation Order Date = Expected Date - Delivery lead time ( in your product definition ---> procurment  tab --> choose any supplier ).

0
Raphael United Kingdom
10/23/13, 1:46 PM

Unfortunately I have not got a work around for it.

0
António Sequeira Portugal
11/19/13, 2:44 PM

Hello,

This is still a real problem. With this way we end up with a wrong sequence of purchase order date vs purchase order number. We are testing a "quick-fix" for this: the purchase order date is the date it's issued. It can never be in the past but it can never be in the future, also. If we send the purchase order for supplier immediately it must have the right date.

Ask a Question
Writer
Keep Informed
4 follower(s)
About This Community

This platform is for beginners and experts willing to share their Odoo knowledge. It's not a forum to discuss ideas, but a knowledge base of questions and their answers.

Register
Odoo Training Center

Access to our E-learning platform and experience all Odoo Apps through learning videos, exercises and Quizz.

Test it now