Odoo 8 Procurement date problem. Scheduled date is not considered

By
Bohdan Lisnenko
on 6/19/15, 5:11 AM 850 views

When SO is confirmed with due date set to next month (for example) Procurement is generated PO with earliest possible date (today + supplier lead). I'm expecting procurement date as late as possible: SO due date - supplied lead time.

Having a lot of SO confirmed to a 1st day of each month is leading to massive purchase scheduled to beginning of the year instead of gradual spread across the year.

I was trying to find scheduler range days parameter which was stated in v7 doc but had no luck.

Product is MTO, reordering rules are set, no realtime scheduler.

About This Community

This platform is for beginners and experts willing to share their Odoo knowledge. It's not a forum to discuss ideas, but a knowledge base of questions and their answers.

Register

Odoo Training Center

Access to our E-learning platform and experience all Odoo Apps through learning videos, exercises and Quizz.

Test it now

Question tools

1 follower(s)

Stats

Asked: 6/19/15, 5:11 AM
Seen: 850 times
Last updated: 6/19/15, 5:11 AM