MO Quantity and Operation Time

By
Stephane
on 8/12/16, 10:57 AM 189 views

I need to preview the cost for a mixing and while the BoM concept is easy, I don't understand how the Routing & Workcenter functionalities work...


Simpliest Use Case:

1 Mixer with capacity 100L

CycleCapacity
Time Cycle
Time Before
Time After
Cost Hour
1
100
40mins
20mins
30mins
42

Now I need to create a Routing to be able to use my mixer. Let's say I create my BoM for a quantity of 100 and then that my routing is for a 100 as well because linked with the BoM 

Name: Mixing

Operation
Number of Cycles
Number of Hours
Mixer

01:30


MO From this situation:

1) Cost is too high because number of hours is 03:00 (doubled) but number of cycles is 1 (ok)

    a) Removing Cycle and Hours from routing = 00:50 but should be 01:30 and cycle is 0 (nok)

2) Changing MO quantity from 100L to 200L do not change the number of hours, but is correct for raw material quantities

3) How to fixe a minimum of work time ? If MO is for 50L then I still need 01:30

4) Before mixing we need to weight each raw materials, how that can be reflect in workcenter ?

Your Answer

Please try to give a substantial answer. If you wanted to comment on the question or answer, just use the commenting tool. Please remember that you can always revise your answers - no need to answer the same question twice. Also, please don't forget to vote - it really helps to select the best questions and answers!

About This Community

This community is for professionals and enthusiasts of our products and services. Read Guidelines

Question tools

1 follower(s)

Stats

Asked: 8/12/16, 10:57 AM
Seen: 189 times
Last updated: 8/12/16, 5:27 PM