Influence MRP date_planned from SO requested_date

By
Tilfried Weissenberger
on 7/17/14, 11:10 AM 729 views

Hi,

currently I can't find a way to schedule a production from within a SO (sales order). The date I set in requested_date does not seem to get used. I would like it to be used as a basis for the MRP date_planned, when the SO is confirmed and the production order is created.

Could anyone point me in the right direction, if this is possible out of the box or can someone give me a hint how I could accomplish this maybe with a workflow or something?

regards, Tilli

anyone?

Tilfried Weissenberger
on 8/5/14, 4:42 AM

anyone?

Tilfried Weissenberger
on 9/2/14, 8:15 AM
0
Gabriel
On 6/1/15, 12:14 PM

Did you try with "Make to Order" AND "Manufacture" route_ids selected for the product procurement?

In order to run the procurement either you click on Warehouse/Schedulers/Run Schedulers menu or activate the "Generate procurement in real time " option in warehouse settings.

0
Matt Taylor
On 11/11/14, 5:42 PM

Sounds like you need to use the Make To Order for products.

I am already using M2O but this does not solve the problem. or what do you mean?

Tilfried Weissenberger
on 11/12/14, 5:14 AM

Your Answer

Please try to give a substantial answer. If you wanted to comment on the question or answer, just use the commenting tool. Please remember that you can always revise your answers - no need to answer the same question twice. Also, please don't forget to vote - it really helps to select the best questions and answers!

About This Community

This community is for professionals and enthusiasts of our products and services. Read Guidelines

Question tools

1 follower(s)

Stats

Asked: 7/17/14, 11:10 AM
Seen: 729 times
Last updated: 6/1/15, 12:14 PM