When i try to add some more work in a task i get this error: ValidateError Error occurred while validating the field(s) state: You cannot modify an entry in a Confirmed/Done timesheet !

I did some work on that task 2 weeks ago, and no i cant do any more because that weeks timesheet is confirmed?

Avatar
Discard

Confirmed This is still broken in lastest 7.0 Nightlies

I know this is an old issue but somehow still not fixed. It also occurs when 2 or more employees have done work on a task and at least one employee has a confirmed timesheet. There is also a launchpad bug related: https://bugs.launchpad.net/openobject-addons/+bug/1229866

Author Best Answer

Tried booth, no luck:(

Avatar
Discard

You should reply to an answer with a comment on the answer, otherwise it appears as if you have already had 2 answers. Sorry I can't help further. Since my answer is no help, I'll delete it.

Best Answer

Are you trying to do this as your own user or as administrator?

(don't forget the "Technical Features" setting)

Avatar
Discard
Best Answer

That's the idea with time sheets. Once it's confirmed you can't modify it. But you still can create analytic entry for project.