How does Odoo determine the reorder quantity based on a rule and multiple orders of procurement (OP)?

Santiago EV
on 11/12/15, 10:48 AM 525 views

I have 2 products in Odoo. One is a very recent product, it has the following characteristics:

OnHand: 71

Incoming: 0

Available: 61 (10 presumably in SO confirmed)

Minimum Reorder Point: 80

OP Procurements: 1

Quantity Reordered by Odoo in OP: 9

This makes sense but for many other products I have a different situation such as:

OnHand: 0

Incoming: 35

Available: 35

Minimum Reorder Point: 254

OP Procurements: 19 (1 to Supplier A, 1 to Supplier B, 17 to Supplier C: All spread out from Aug 2015 until Nov 2015)

Quantity Reordered by Odoo in OP: 224 in all 19 orders (35 in PO Supplier A, 1 to Supplier B and 188 to Supplier C)

My issue is, my mrp engine is set to run everyday at midnight. Procurements are not generated daily, replacing some old value. How does odoo generate these requriements? And how should I interpret what odoo is suggesting?

Your Answer

Please try to give a substantial answer. If you wanted to comment on the question or answer, just use the commenting tool. Please remember that you can always revise your answers - no need to answer the same question twice. Also, please don't forget to vote - it really helps to select the best questions and answers!

About This Community

This community is for professionals and enthusiasts of our products and services. Read Guidelines

Question tools

1 follower(s)


Asked: 11/12/15, 10:48 AM
Seen: 525 times
Last updated: 11/12/15, 10:50 AM