I'm having some issues with the MRP in Odoo 9 I've created correctly the BoM for a product as well the work center and the routing.

Both the final product as the raw materials are tracked by Lots.

When I create a manufacturing order, it  doesn't let me consume the raw materials (selecting the correct lots) if I don't click on Produce button. 

it appears the error:

Because the product ********** requires it, you must assign a serial number to your raw material ########## to proceed further in your production. Please use the 'Produce' button to do so.

I'f I use the produce button, the manufacturing order goes to finished stage instantly.

Sure that something isn't correctly configured but what is it?


Avatar
Discard
Author Best Answer

But the raw material is configured with tracking by lots.  Even if I select all the Lots of the raw materials it doesn't let me consume them. Only if i hit the produce button.

Avatar
Discard
Best Answer

My guessing is Raw Material product doesn't mapped with any serial number

From lot/serial number menu you can create it