I'm trying to have the procurement scheduler execute as per the reordering rules but the scheduler seems not to execute to create PO.
On the product purchase tab i already have a vendor set with the right quantiles, price and dates.
I have the Reordering Rules with correct min - max units.

And the routes on inventory tabs are on buy and MTO. Firing the scheduler manually is not helping either. My time zone is OK

Please help

Avatar
Discard
Best Answer

To be able to reorder the product, the forecasted product qty must be below min quantity set on reordering rule.
MTO (replenish on order) is used to prepare RFQ immediately after sales order confirmation. Only Buy route is needed for reordering rule. 

Avatar