This question has been flagged
1 Reply
788 Views

after cutting washer, I put 250 pcs in a box. how can I create the BoM so that it rounds up the box qty when it comes to manufacture?

BoM

   Washer qty=1 Ea

      Sheet metal       qty=10 sq.cm

      Box (250/box)   qty 0.004 box.


Is there any way to set up the UoM, accuracy, precision, bom to always give me a round up in boxes?


example.

MO

Washer Qty needed = 400

   sheet metal  required = 4000sq.cm

   Box (250/box)   required = 2 boxes


(not 1.6 boxes)

Avatar
Discard
Author Best Answer

I created a BoM and it works, however, the Precision of UOM must be set to 1.0 not less

Washer Qty = 250 Ea

   Sheet.....

    Box Qty = 1 box.

Now it is rounding off to closest. However what threw me off was when I manually changed the Qty on the MO the Qty of box was fraction and no longer rounded off.



Avatar
Discard