This question has been flagged
2 Replies
3483 Views

When I calculate price from BoM I get only product cost, not BoM Cost including cost of Operations.

Have I overlooked some settings? The information square that pops up when hovering "Compute Price fron BoM" says "Compute the price of the product using products and operations of related bill of materials"

Also posted in forum for MRP Course, sorry for cross posting.

Avatar
Discard
Best Answer

I have this same exact issue if someone can help me. I would like the compute bom cost to come from the bom cost, but it gives me a random number that is not the product cost or the bom cost. 

I am using avco and automated inventory valuation as well.

Avatar
Discard
Best Answer

Yes you are missing something.

- Are you using FIFO or AVCO, or manual valuation? You need to use an automatic system (either will work).

- Check you have set your work center properly, and that you have included a cost per hour.

- Check the operation time is not set to 0.

Avatar
Discard

The product cost and the BOM cost are different columns in the bom overview report. The compute BOM cost seems to add the product costs up not the BOM costs, which is a case of heavy labor can vary a lot. How can we get it to use the BOM cost and not the product cost? I think that is what he is asking and is the same issue I have.

Author

Hej,

Jag är på semester och kommer tillbaka 7/8, v32.


Vänligen

Johannes Törnqvist

Alstermo Bruk

0700009088

Related Posts Replies Views Activity
0
Aug 23
1581
2
Jan 22
4500
1
Dec 20
2165
1
Apr 20
2152
1
Mar 15
3623