I have a query on task planning in project and Planning Module of Enterprise version 15


  • When we are creating a task in project and assigning to an employee it is not reflecting in the planning module.


  • When we create a planning and a task to a resource from planning module it is not reflecting in project module / the assignee is not changing or added


  • If a task is assigned in the same period for an employee and it shows a notification of the conflict in planning but it doesn't shows the task if it is from the project module


Here this creates confusion in the working of the planning module. If it is not for task planning based on Project and field service module then what is the exact purpose of that module


This will create duplication and conflicts in the task planning 


Kindly advice with solutions.


Avatar
Discard
Best Answer

I have same issue, and version 16, they are not linked together between Planning Module and Planning from Project Module. So we have to manage manual between 2 apps, it's really bad Planning ever.