2 Answers
0
Avatar

Pinakin Nayi (pna)

--Pinakin Nayi (pna)--
1749
| 2 2 7
Ahmedabad, India
--Pinakin Nayi (pna)--

He has good skills in problem identification and implementation of effective solutions. He is working in Odoo India.

Techno-Functional
Skype: pinakinerp

LinkedIn : https://www.linkedin.com/in/pinakin-nayi-2a33103a/

 

Pinakin Nayi (pna)
18/1/19 5:24

Yes, based on your demand you have to manually set the forecasted stock. Also you can set buffer stock and based on this all you can generate MO or PO either by manually or by scheduler automatically generate. This will also consider your lead time, so you can check the qty needed in particular month/period.

Ex. If you want to manufacture 100 units of product A in April month then you can set the demand and based on that MPS report shows you the in which month the related components needed(based on lead time).

2 Comments
Véronique Piveteau
18/1/19 5:38

OK for this step.

How does it work with logisitcs routes already in use ?

For ex: actually, the mto mts module + produce route generates orders in the system (MO or PO) based on lead times for each SO

MPS generates also orders based on lead times for forecasts

Do I have to choose between them ?

Véronique Piveteau
18/1/19 5:39

OK for this step.

How does it work with logisitcs routes already in use ?

For ex: actually, the mto mts module + produce route generates orders in the system (MO or PO) based on lead times for each SO

MPS generates also orders based on lead times for forecasts

Do I have to choose between them ?

Realizar una pregunta
Keep Informed
1 seguidor(es)
About This Community

This platform is for beginners and experts willing to share their Odoo knowledge. It's not a forum to discuss ideas, but a knowledge base of questions and their answers.

Register
Odoo Training Center

Access to our E-learning platform and experience all Odoo Apps through learning videos, exercises and Quizz.

Test it now