We manufacture sewn goods and have several sewers at their own sewing stations. This means that I can distribute one set of materials and have the sewers produce goods at the same time: five sewers can make one unit each. For Odoo, there's only one sewer producing five units because it will not distribute operations across alternative workcenters.

(The "Capacity" feature does not solve my issue. That makes the work center output multiple units with one cost unit. That's different than what I described above.)

Is there any way to setup products and BoMs to workaround this limitation?