 Hello Seniors ,

Now , I want to know Can we assign multi users to one task in odoo project management module?Please kindly answer to me. Your help is highly appreciatively.Thanks.

Avatar
Zrušit
Nejlepší odpověď

Yes, one Task can have only Responsible person.

But it's possible to "assign" several people to the same Task using the record "Work on Task" option: this adds to Tasks a grid to record time on tasks, and each line can correspond to a different person.

It's meant to record time spent on tasks, but you could also use it to plan people assigned on Tasks: just leave the Time/Hours spent as zero when assigning people to it. Later on you can edit them to record the real time spent. if you wish.