This question has been flagged

I added 2 selection fields from studio, first one on the project.project model and the 2nd one on the project.task model, both selection fields contain same value:  Not Started, Ongoing, Done. I need to automate the following:

When all the tasks related to a project have their status set to 'Done' thus the project status should also set to 'Done'.


How to achieve this using Studio only??

Avatar
Descartar

You can do that using automated action

Autor

Can you demonstrate an example, since I tried it but didn't reach a solution