Hi,

I'm working on Odoo v10 and I'm having issues to understand what's happening on how Odoo calculate time on tasks and sub-tasks. 

I've created a test project. 

Inside of that project, 

I've created two tasks: task A and task B.

Inside task A, I've created two sub-tasks: sub-task 1 with 10h initial hours and sub-task 2 with 5 initial hours. 

When I go to Search > Tasks and create a pivot table and select: initial hours, spent hours and remaining hours, I get this:

Task A | 0 initial hours | 0 spent hours | 0 remaining hours

Sub-task 1 | 10 initial hours | 3 spent hours | 7 remaining hours

Sub-task 2 | 5 initial hours | 4 spent hours | 1 remaining hours

Although the math on the Sub-tasks are correct, those values don't revert back to the ascending task, Task A. Therefore, I can't get a correct reading on the task status. 

What I would like to see is a sum of all from the sub-tasks added to the values inserted on the Task itself. This way I can monitor the progress of the task and of the underlying tasks. 


Is this a bug or I'm doing something wrong?


Thanks in advance.

  

الصورة الرمزية
إهمال
أفضل إجابة

it nothing wrong, odoo do not make it normal correct working. so you need  to find custom addon or customise.

الصورة الرمزية
إهمال
المنشورات ذات الصلة الردود أدوات العرض النشاط
2
يونيو 24
1524
2
مارس 24
2225
0
فبراير 24
1653
2
أكتوبر 23
1863
Project and Tasks تم الحل
1
يوليو 23
2026