Procurment orders are in red when date_planned>current_date and state='exception' 

see: addons/procurement/procurement_view.xml ->  id=procurement_tree_view
(for v7.9 it is in line 9, and board in line 31)

So change your customer lead time from 3 to 7 days on products form,
and it will make date_planned 7 days ( no harm if it comes earlier) 

hope it helps..